SCORELINEPARTNERS 780-792-1928 Book a 30-minute look Call

Quick quote estimating

Price the job from your own field data.

Pick the assemblies and the quantities. Crew-hours come from your own past jobs, prices from the client’s rate sheet. Small jobs are priced in minutes; big tenders go on the owner’s unit-price bid form. When you win, the quote becomes the job.

Quoted after scopingQuoted after we scope your assemblies and rate sheets. CAD, plus GST.All prices

  • Assemblies
  • Production rates
  • Client rate sheets
  • Tender mode
  • Estimate vs actual
  • Rate library
Quick quote: client and job, assemblies with quantities and crew-hours per unit from past jobs, and totals for labour, equipment and materials. Sample data.

What it fixes

Quotes from memory lose money quietly.

Before

A spreadsheet per estimator

Every estimator has their own sheet and their own numbers, and none of them match what the crews actually take.

NowOne library of assemblies, with crew-hours from your own finished jobs.

Before

Small jobs, slow quotes

A service call waits days for a price, and the client calls someone else.

NowPick assemblies and quantities on the client’s rates. Small jobs priced in minutes.

Before

Nobody checks the estimate

The job finishes, the numbers are never compared, and the next quote makes the same mistake.

NowEstimate vs actual on every job, from the signed LEMs, feeding the rate library.

How it works

Assemblies in. A price out.

Each assembly carries its crew, its equipment and the crew-hours per unit your crews have actually taken. Pick the quantities; labour, equipment and materials price themselves on the client’s rates.

  1. Quote
  2. Awarded
  3. Work plan
  4. FLRA
  5. LEMs
  6. Estimate vs actual
  7. Rate library
Q-26-118 · replace 6 poles, 3 spansSample rates
AssemblyQtyCrew-hAmount
Mob/demobLine crew, local1 job6.0$4,719
Set distribution pole45 ft Class 3 · from 23 poles632.4$26,053
Framing, 3-phase tangentfrom 41 structures618.0$9,880
Transfer conductorper span · from 17 spans321.6$11,740
Traffic controlper day2—$3,600
Total before GST$55,992

Tender mode

The big ones, on the owner’s bid form.

The owner’s unit-price schedule, priced from the same assemblies and your own production rates, balanced to the estimate.

  • Loaded labourCrew types and rotations, priced on your own labour costs.
  • Owned and rented equipmentYour own fleet at its rates; rentals by the calendar day.
  • Supplier quotesCompared side by side, with plugs where a quote hasn’t come in.
  • Indirects and markupField and head-office indirects, contingency, bonds and insurance, each visible.
  • Cash flowWith holdback, so you know what the job needs before you sign.
  • Award to jobThe won tender becomes the job, the work plan and the progress claims.

Questions

About Quick quote.

Priced by company size, not per seat. Fixes and updates included in every monthly.

Where do the production rates come from?

From your own past jobs. Each assembly carries the crew-hours your crews actually took, and estimate vs actual on every finished job feeds back into the rate library.

Can it price on our client’s rate sheet?

Yes. Quotes are priced on the client’s schedule of rates you pick for the job.

Can we bring estimates in from HeavyBid?

Yes. HeavyBid estimates can be imported, so the work you’ve already priced comes with you.

What happens when we win?

Mark it awarded and the quote becomes the job: the work plan, the hazards on the FLRA, the LEMs and the invoice all start from it.

Next step

Bring your last three quotes.

We’ll rebuild one in front of you from your assemblies, and show you where the actuals went.

Fort McMurray, Alberta · serving contractors across Canada