01Two weeks, a hundred LEMs
“I used to be on the owner’s side. One year I went on holidays and forgot to hand off my approvals. I came back two weeks later to over a hundred LEMs sitting in Fieldglass, waiting on me. Finished work. Nobody could bill it. And the contractor’s payroll still went out every two weeks. We didn’t lose a thing. The contractor carried all of it.”
What it cost100 LEMs × ~$2,500 = ~$250,000 of finished work that couldn’t be invoiced for two weeks. Payroll went out anyway.
What changesThe contractor sees on day two who each LEM is waiting on, and goes to the backup. Not in week three.
02Book a meeting to get a signature
“A field supervisor on the owner’s side covers a huge area. The odds of them crossing paths with you during the day? Not great. You end up almost booking meetings, just to get your LEMs signed.”
What it cost2 hours a week chasing × $45/h × 52 = ~$4,700 a year, for each person doing the chasing.
What changesThe LEM goes to their phone. They check the hours and sign wherever they are, in about a minute.
“Contractors drive thirty minutes or more out to site, just to get one LEM signed. They get there, and find out he’s off. That’s an hour of a foreman’s day, and a truck, gone. Then you do it again tomorrow.”
What it costOne wasted trip a week × (1 hour of a foreman ~$65 + truck ~$40) × 52 = ~$5,500 a year.
What changesThe LEM goes to him. If he’s off, it waits on his phone, or it goes to whoever’s covering.
“One line on a LEM needed changing. It took two weeks to get the first signature. Then the approver went on vacation for four weeks. No out-of-office on. That LEM was over fifteen thousand dollars, and we’d rented special equipment just for that job.”
What it cost$15,000+ outstanding for six weeks, with the rental already paid out.
What changesThe client flags the one line, you fix it in the LEM, and they sign again from their phone. Nobody’s opened it in a couple of days? You know, and it goes to whoever’s covering.